Project Information:
The purpose of the contracts in the context of which the bridges/structures' were designed, is the construction of a motorway that will bypass the urban complex of Arachova and will facilitate traffic to Delphi-Itea and to the adjacent Ski Center, and minimize the adverse environmental problems that accumulate in Arachova due to traffic.
The bridges/structures will be developed around 3 basic intersections.
Eastern Interchange
- Bridge Γ1 with 3 spans, a total length of 92,64m. and a superstructure of precast prestressed T-beams.
- Bridge Γ2 with 4 spans, a total length of 155,00m. and a superstructure of precast prestressed T-beams.
- Bridge Γ3 with 7 spans, a total length of 178,00m. and a superstructure of prestressed box-girders with seismic expansion joints.
- Access Structure to Bridge Γ3 Reinforced Concrete Box-type Structure, with a length of 19,80m.
- Pilewalls with a total length of 360,00m.
Western Interchange & At-grade Intersection
- Bridge Γ5 with 3 spans, a total length of 85,00m., and a superstructure of a twin reinforced concrete box-girder.
- Bridge Γ7.1 with 3 spans, a total length of 76,00m., and a superstructure of a reinforced concrete box-girder.
- Bridge Γ7.2 with 4 spans, a total length of 101,00m., and a superstructure of a reinforced concrete box-girder.
- Bridge Γ7.8 with 1 span, a total length of 14,20m., and a superstructure of a twin reinforced concrete box-girder.
- Γέφυρα Γ8 with 1 span, a total length of 14,86m., and a superstructure of a twin reinforced concrete box-girder.
- Pilewalls with a total length of 980,00m.
Client: Ministry of Infrastructure and Transportation
Date: 2009 – 2019 & 2022-2023 (2 Contracts)
Location: Arachova, Boeotia-Greece
Estimated Cost of Construction: 35.000.000 €
Scope of Work:
Based on our contractual obligations our firm provided the following services:
- Bridges and Structures Schematic Design
- Structural Final (Detailed) Design of Bridges/Structures and Design of Foundations
- Preparation of Tender Documents